OUTCO Tesco Bedford resurfacing

Tesco Bedford

Following a site review highlighting critical areas requiring repair, including severe pot holes, faded line marking and damaged civils elements, we were instructed by the client to complete a full resurfacing of the entire car park and entrance road to the superstore.

Tesco Bedford

SURFACING LINE MARKING | CIVIL ENGINEERING | DRAIN SURVEYS | DRAIN REPAIR

As retail specialists, we were approached by Tesco to complete critical surfacing repairs to the dilapidated car park at Tesco Bedford.

Following a site review highlighting critical areas requiring repair, including severe pot holes, faded line marking and damaged civils elements, we were instructed by the client to complete a full resurfacing of the entire car park and entrance road to the superstore.

Our team in the south worked on the project for three weeks, phasing repairs to ensure minimal disruption to the store and busy Click and Collect unit.

Delivery

This project required the resource of several divisions within the Infrastructure Compliance team, from our initial site surveying team, CCTV drainage to our surfacing, line marking and drainage remedial teams.

The 21,000m² resurfacing project was completed in three weeks and transformed the car park.

Our drainage team completed a CCTV survey prior to the works ensuring no severe issues beneath the surface were apparent that could cause further problems to the car park surface in the future, remedials were repaired using a no dig technology ensuring no excavation occurred.

Our civils team were also on site completing bollard repairs and installation, tactile paving repairs and replacing the defective ACO drainage channels across site. The site was completed with fresh line marking, returning the car park to its original layout.

The Store Manager was thrilled with the works “Thanks for this really great job. A huge thank you from me”

Tesco Bedford Car Park Resurfacing

Tesco Bedford Car Park Resurfacing